E-mobility charging infrastructure

This is where you can find information about connecting e-mobility charging infrastructure.

Information on connection applications

Please note that infrastructure connections require consent in accordance with the network operator's technical low voltage grid connection requirements (TAB NS Nord, 2016 edition)

We recommend that you seek the advice of an installer from the list of installers when applying for your house connection or when planning to change your existing connection. This avoids delays in the construction process and ensures that the project can be executed from a technical point of view in accordance with the technical low voltage grid connection requirements (TAB NS Nord).

search for contact person

Please also note the additional information that applies to each house connection:

New house connection

You can get an overview of the process and requirements for setting up a new house connection in the leaflet "The electrical connection - fact sheet for developers and architects" (PDF 8 MB).

Required documentation:

  • "Grid connection application" (PDF 554 kB) form
  • detailed performance listing (depending on planned construction measures: e.g. number of apartments, type of hot water provision, number of business units, type of business, technical building performance specifications)
  • Construction site address and developer address and, if different: the address to which the quotation should be sent
  • scale site plan and/or cellar floor plan showing the desired location of the house connection to be installed.

 

Please also note the information on requesting the connection and the next steps.

Increasing capacity

To increase the capacity of an existing house connection, we require the following documents:

  • "Grid connection application" (PDF 554 kB) form
  • detailed performance listing (depending on planned construction measures: e.g. number of apartments, type of hot water provision, number of business units, type of business, technical building performance specifications)
  • Construction site address and developer address and, if different: the address to which the quotation should be sent
  • scale site plan and/or cellar floor plan showing the location of the house connection.
Please also note the information on requesting the connection and the next steps.

 

Costs

The current costs of installing/changing a house connection are listed on our price sheet.

Price sheet for low voltage grid connections (PDF 60 kB)

 

Contract documents

Persons authorised to carry out electrical installation work

Are you looking for an electrician to install your charging infrastructure?

All electrical firms registered in our installer directory are authorised to connect charging infrastructure. Our Installer Search tool can help you find a company in your region.

Go to Installer Search

More information is also available on the Elektro-Innung Berlin website (German only). This is where the e-mobility working group publishes additional information and a list of specialised firms for: http://www.elektroinnungberlin.de/index.php?id=1598

The next steps in the process

Please send us - via your installer if applicable - your completed documentation: kundenanschluesse@stromnetz-berlin.de.

Once you have made this application, you will receive a quotation with further documents. By signing the quotation and, if applicable, the grid connection agreement, you are contractually commissioning the connection.