Temporary connection

Supplying energy to a construction project, street party, market or other type of event requires a temporary connection.

You can find information on temporary low voltage grid connections in the "Temporary connections with connection and distribution boxes" guide available as a download.

Street party, market or event

Supplying energy to a street party, market or another type of event requires a temporary connection.

We require the following documents and information to process your request:

  • Dates of the event
  • Sketch/map of the event site
  • Specifications of the required output (kW)
  • The address of the event location and the address of the applicant (if different: the address to which the quotation should be sent)
  • Applicant's telephone number (and additional contact details if required)

To ensure that your request can be processed properly, please contact us well before the intended start of the event.

The cost of the temporary connection is calculated individually for each customer after the event has finished.

Please send your request to strassenland@stromnetz-berlin.de.

Electricity supplies for construction sites

Supplying energy to a construction project requires a temporary connection.

We require the following documents and information to process your request:

  • The completed "Grid connection application" form available as a download
  • Specifications of the required output
  • The address of the construction site and constructor (if different: the address to where you would like us to send the offer)
  • If you plan to use cranes: crane type and data
  • Construction site map
  • Applicant's telephone number (and additional contact details if required)

To ensure that your request can be processed properly, please contact us well before the intended start of the construction project..

Information on connection applications

We recommend that you seek the advice of an installer from the list of installers when applying for your house connection or when planning to change your existing connection. This avoids delays in the construction process and ensures that the project can be executed from a technical point of view in accordance with the technical low voltage grid connection requirements (TAB NS Nord).

Warning:

  1. Please note that you will need to agree the energy supply for your event and/or construction project separately with an energy supplier of your choice.
  2. 1.Please refer to our information on the medium-voltage grid connection page if you require your own construction site energy station to generate the electricity needed for your construction project.

Are you looking for an electrician?

An Electrician will be happy to assist you with any questions you may have regarding your temporary Connection..

Please use our electrician search function to select a specialist electrical company registered with Stromnetz Berlin.

Installer search