Publication of the results of grid losses tender

Stromnetz Berlin GmbH invited tenders to procure energy to cover energy losses.

The results of these tenders, of which the scope was determined by decision BK6-08-006 made by the Bundesnetzagentur (Federal Network Agency) on 21 October 2008, can be seen in the following.

Point 10 section c) sub-point aa) in the decision regulates the information about price limits for long-term components.

Point 11 section e) sub-points aa) and bb) in the decision regulate the information about remuneration of the service provider which gained the last tender for short-term components and the historical energy losses load profiles.

Price limits for long-term components

The following price limits were targeted by the tenders executed.

Year of delivery

Date of tender

Price limit
(EUR/MWh)

2019

06.12.2017

37.02

2019

16.11.2017

37.75

2019

26.10.2017

36.34

2019

07.09.2017

33.11

2019

10.08.2017

31.38

2019

13.07.2017

31.21

2018

22.06.2017

33.15

2018 11.05.2017 31.23

2018

27.04.2017

31.35

2018

30.03.2017

31.03

2018

23.02.2017

33.15

2018

26.01.2017

31.31

2018

15.12.2016

30.18

2018

10.11.2016

32.16

2018

20.10.2016

30.44

2018

29.09.2016

29.47

2018

25.08.2016

26.40

2018

21.07.2016

28.13

2017

23.06.2016

29.77

2017

12.05.2016

26.33

2017

28.06.2016

26.61

2017

17.03.2016

23.14

2017

25.02.2016

22.82

2017

28.01.2016

25.25

2017

17.12.2015

28.23

2017

26.11.2015

29.39

2017

29.10.2015

30.30

2017

24.09.2015

30.70

2017 13.08.2015 32.51
2017 30.07.2015 33.33

2016

25.06.2015

33.57

2016

28.05.2015

33.01

2016

23.04.2015

33.49

2016

11.03.2015

33.87

2016

26.02.2015

35.49

2016

28.01.2015

34.13

2016

09.12.2014

36.94

2016

26.11.2014

38.22

2016

22.10.2014

35.61

2016

24.09.2014

36.46

2016

27.08.2014

37.09

2016

30.07.2014

36.68

2015

25.06.2014

36.92

2015

22.05.2014

37.08

2015

23.04.2014

37.25

2015

26.02.2014

38.15

2015

12.12.2013

39.78

2015

24.10.2013

39.84

2015

29.08.2013

38.67

2014

20.06.2013

40.85

2014

25.04.2013

42.22

2014

28.02.2013

44.68

2014

12.12.2012

49.45

2014

25.10.2012

51.12

2014

16.08.2012

53.17

2013

19.06.2013

50.61

2013

18.04.2012

54.48

2013

21.02.2012

55.59

2013

06.12.2011

55.83

2013

27.10.2011

57.87

2013

31.08.2011

62.02

Remuneration for short-term components

The service provider who supplied short-term components for the corresponding tender was remunerated as follows.

Year of delivery

Date of tender

Remuneration
(EUR)

2018

05.12.2017

1,909

2017

01.12.2016

2,000

2016

10.12.2015

2,184

2015

16.12.2014

2,487

2014

28.11.2013

2,760

Amount and total load of grid losses

Data on grid losses on the distribution grid as an amount of energy and the temporal curve of the total load of grid losses.

The grid losses as an amount of energy were found by calculating the difference between feed and withdrawal.

The total amount of grid losses for Berlin's distribution grid in 2016 amounted to 404,403,412 kWh.
The amount is determined through calculations.

Total load of grid losses

The total load of grid losses is the load profile of the grid losses across all grid and voltage levels as 1/4h performance values. The performance values are determined through calculations.

Historical load profiles total load of grid losses (XLS 7 MB)

Total load of grid losses 2016 - load curve (CSV 953 kB)

Total load of grid losses 2015 - load curve (CSV 951 kB)

Total load of grid losses 2014 - load curve (CSV 950 kB)

Total load of grid losses 2013 - load curve (CSV 950 kB)

Total load of grid losses 2012 - load curve (CSV 824 kB)

Total load of grid losses 2011 - load curve (CSV 822 kB)

Total load of grid losses 2010 - load curve (CSV 957 kB)

Total load of grid losses 2009 - load curve (CSV 925 kB)

Total load of grid losses 2008 - load curve (CSV 2 MB)

Total load of grid losses 2007 - load curve (CSV 989 kB)

Total load of grid losses 2006 - load curve (CSV 852 kB)

Decision of the Federal Network Agency

Establishment of the Tendering Process for Energy Losses and the Process for Determination of Grid Losses (BK6-08-006) (PDF 122 kB)

All downloads are available in German language only.

Disclaimer

The data published here were produced and prepared for release with the greatest care. Nonetheless, errors in recording and transmission cannot be ruled out. Stromnetz Berlin GmbH therefore expressly reserves the right to change the published data at any time and assumes no responsibility for its accuracy. If arrangements are made based on the data published which lead to damages to the user or a third party, Stromnetz Berlin GmbH cannot be held liable unless they were aware of the data's inaccuracy at the time of publication and intended to damage the user or a third party.