Expansion of the electricity grid: new cabling for residential development in Pankow

There are plans to increase municipal housing construction in the north of Pankow over the next few years, while also increasing the number of wind turbines.

However, the medium voltage grid for the "Falkenberger Straße" transformer station supply area is not designed to accommodate this growth and requires expansion and/or renovation. Over several phases of construction, there is a requirement to create two new 10 kV grid rings and to extend an existing 10 kV grid ring. In carrying out this work, synergies with the "B2 Dorfstraße Malchow" road expansion are being considered. In addition to adapting our sections of cable, some work is also needed on Falkenberger Straße transformer station.

The expansion work will primarily take place on cycle paths and pavements. However, it may include disruption on the road (e.g. road closures on one side or lane restrictions).

There are no disruptions to the electricity supply planned. However, if short disruptions do become necessary, we will inform affected customers well in advance – at least three working days beforehand – by putting up notices. We would like to apologise in advance for any inconvenience that this may cause and ask for your understanding.

Construction phases in overview

Phase Activity Period
1 - closed Laying a new cable run along the B2 to behind the Malchow high-voltage transformer station, as part of expanding the grid to include EEG assets October 2017 - May 2018

2 - closed

Expansion of cable runs and laying of cables along Blankenburger Pflasterweg October 2017 - May 2018
3 - closed Laying cables along Dorfstraße Malchow 1th and 2ndQuarter 2018
4 - closed Laying cables along Hohenschönhauser Weg November 2017 - July 2018
5 Laying cables along Kyllburger Weg January 2019 - March 2020

If you have any questions or comments on these building works, please get in touch with a member of staff using the contact details provided. The company HAN Netzbau GmbH will carry out excavation work for construction phases 1 to 3.