Skip to main contentSkip to navigationSkip to search

Our service

Customer requests 030 49202 0294

Monday - Friday, 8am - 5pm

Expansion of the Amalienhof substation

Planned expansion

We are investing in the future in your district and thus in maintaining and expanding a secure energy grid.

More and more charging stations for electric vehicles, photovoltaic systems on roofs or balconies are shaping Berlin’s urban landscape. And Berlin’s electricity grid will also cover part of the heat supply in the future. To ensure that our power grid is set up to cover all these tasks reliably, we are renewing and expanding the Amalienhof substation.

Up-to-date construction information

  • 2nd quarter 2024 to 1st quarter 2025: Site clearance, preparatory construction work such as creating the excavation pit and shoring

  • 2nd quarter 2025 to 3rd quarter 2026: Shell construction of the new substation

  • 3rd quarter 2026 to 2031: equipping the substation with the electrical systems

  • Expected from 2031: Dismantling of the old substation

  • 2031/2032: Construction of the outdoor facilities on the site, such as green spaces or lighting.

  • Work starts on the construction site between 6am and 7am on working days. Working hours end at 6pm at the latest.
  • Access to private properties will remain open. However, there will be restrictions on public roads.
  • Escape routes will remain open at all times.

Flyer "Power grid renovation in the Amalienhof"

In German language only.

Contact

Yvonne Post
Consultant Citizen Dialogue

T 030 49202 0294
(Customer contact, Mo - Fr, 8am - 5pm)

buerger-innendialog@stromnetz-berlin.de