Replacement construction of the Mitte grid node
We are investing in your neighbourhood’s future, and thus in maintaining and expanding a secure electricity grid.
More and more charging stations for electric vehicles and photovoltaic systems on roofs and balconies are shaping Berlin’s cityscape. And in future, Berlin’s electricity grid will also be used for part of the heat supply. To ensure that our electricity grid is reliably equipped for all these tasks, we are modernising and expanding our Mitte grid node.

Visualisation new building - street view (Animation: ICL)
Information on the planned construction work
The construction project is divided into the following construction phases:
- Q3 2024 bis Q1 2025: Construction site equipment
- Q3 2024 bis Q2 2025: Installation of cable conduits
- Q2 2025 bis Q3 2025: Above-ground demolition of an office and warehouse building
- Q3 2025 bis Q2 2026: Demolition of the foundation and construction of the excavation pit
- Q2 2026 bis Q2 2027: the new building is under construction
- Q2 2027 bis Q4 2027: The façade of the building is constructed and the interior work is carried out
- Q1 2028 bis Q2 2030: Installation of the system technology and commissioning
- Q2 2030 bis Q3 2032: The 110 kV cables are swivelled to the new grid node
- Q3 2032 bis Q2 2034: The systems in the old network node are dismantled
Start of work and restrictions
- Work starts on the construction site at around 7.00 a.m. on working days.
- Working hours end at 8.00 pm at the latest.
- Access to the private properties will be maintained.
- There will be restrictions on public roads.
- Escape routes will remain open at all times.
- There will be no planned power interruptions.