Construction Amalienhof substation
We are investing in the future in your district and thus in maintaining and expanding a secure energy grid.
More and more charging stations for electric vehicles, photovoltaic systems on roofs or balconies are shaping Berlin’s urban landscape. And Berlin’s electricity grid will also cover part of the heat supply in the future. To ensure that our power grid is set up to cover all these tasks reliably, we are renewing and expanding the Amalienhof substation.
Up-to-date construction information
- 2nd quarter 2024 to 1st quarter 2025: Site clearance, preparatory construction work such as creating the excavation pit and shoring
- 2nd quarter 2025 to 3rd quarter 2026: Shell construction of the new substation
- 3rd quarter 2026 to 2031: equipping the substation with the electrical systems
- Expected from 2031: Dismantling of the old substation
- 2031/2032: Construction of the outdoor facilities on the site, such as green spaces or lighting.
- Work starts on the construction site between 6am and 7am on working days. Working hours end at 8pm at the latest.
- Access to private properties will remain open. However, there will be restrictions on public roads.
- Escape routes will remain open at all times.