Replacement construction of the Wittenau grid node
We are investing in your neighbourhood’s future, and thus in maintaining and expanding a secure electricity grid.
More and more charging stations for electric vehicles and photovoltaic systems on roofs and balconies are shaping Berlin’s cityscape. And in future, Berlin’s electricity grid will also be used for part of the heat supply. To ensure that our electricity grid is reliably equipped for all these tasks, we are modernising and expanding our Mitte grid node.
Information on the planned construction work
We will build a new network node between summer 2024 and the end of 2028. It will go into operation in 2029 and replace the old network node.
The ground-breaking ceremony for the project took place on 19.06.2024.
Start of work and restrictions
- Work starts on the construction site at around 7am on working days.
- Working hours end at 8pm at the latest.
- Access to the private properties will be maintained.
- There will be restrictions on public roads.
- Escape routes will remain open at all times.
- There will be no planned power interruptions.