Restructuring of grid in Treptow-Köpenick

To increase capacity and improve security of supply, we are laying new high-voltage cables in the district.

The images are intended to illustrate underground cable construction work and do not depict any of the upcoming construction sites.

Berlin's increasing demand for electricity makes it necessary to expand the power grid. We will therefore more than double our capacity by 2033.

From the second quarter of 2025, new high-voltage cables will be laid in Treptow-Köpenick for this purpose. The construction work is expected to be completed by the third quarter of 2026.

Construction work schedule

The cable work will be carried out during ongoing operations. In order to ensure the power supply at all times, the planned work will be carried out sequentially in different construction phases.

The grid restructuring covers the districts of Adlershof Ost, Spindlersfeld and Altstadt-Kietz Köpenick. The following streets or sections of streets are affected by the measures:

Streets respectively sections of streets Activities 
Alter Markt (Landjägerbrücke)

New traffic regulation order follows for further exploratory excavation

Dörpfeldstraße Not being built on
Flemmingstraße

Cable underground construction completed

Flushing borehole from 02.10.2025

Freystadter Weg Completed
Gellertstraße Completed
Gutenbergstraße Flushing borehole from 02.10.2025
Landjägerstraße Extended until early October 2025
Lohnauer Steig Temporary construction site area extended until the end of October 2025
Oberspreestraße Exploratory trench completed
Radickestraße

Completed except at the Nipkowstraße intersection

Selchowstraße

Completed

Thomas-Müntzer-Straße Completed
Wassermannstraße

1. Section from 28.07.2025

2. Section behind Dörpfeldstraße from 01.09.2025 completed

3. Pressure via Dörpfeldstraße with civil engineering work starting on October 6, 2025. Pressure from the beginning of November 2025

Wünschelburger Gang Completed
Zinsgutstraße

Completed and opened to traffic

Temporary asphalt, concrete restoration to follow

Expected disruptions during construction work

  • During construction work, there will be temporary restrictions/partial closures on public roads.
  • Temporary noise is to be expected during construction work on weekdays from 7 am to 8 pm (depending on the season).

Note: Emergency routes and access to private properties will remain open.

Contact

Yvonne Post
Consultant Citizen Dialogue

T 030 49202 0294
(customer contact, Mo-Fr, 8 am - 6 pm)

[email protected]

Broschure Restructuring of grid in Treptow-Köpenick

in German language only