Restructuring of grid in Treptow-Köpenick

To increase capacity and improve security of supply, we are laying new high-voltage cables in the district.

The images are intended to illustrate underground cable construction work and do not depict any of the upcoming construction sites.

Berlin's increasing demand for electricity makes it necessary to expand the power grid. We will therefore more than double our capacity by 2033.

From the second quarter of 2025, new high-voltage cables will be laid in Treptow-Köpenick for this purpose. The construction work is expected to be completed by the third quarter of 2026.

Construction work schedule

The cable work will be carried out during ongoing operations. In order to ensure the power supply at all times, the planned work will be carried out sequentially in different construction phases.

The grid restructuring covers the districts of Adlershof Ost, Spindlersfeld and Altstadt-Kietz Köpenick. The following streets or sections of streets are affected by the measures:

Streets respectively sections of streets Activities 
Alter Markt 

Completed

Flemmingstraße

Work on the drinking water line, followed by surface restoration 

Freiheit

Completed

Freystadter Weg

Completed - cable assemblies

Closed until June

Gellertstraße

Completed; full closure due to cable trenching and underground connection work, expected to last until August 2026

Landjägerstraße

Completed as of April 9; cable trench open until August 2026

Lohnauer Steig Completed – Cable installation: Trench to remain open until the end of July 2026
Lüdersstraße Roadworks until mid-May 2026
Oberspreestraße Civil engineering works are expected to continue until mid of July 2026
Radickestraße

Completed except for the Nipkowstraße junction

Cable trench until 1 July 2026

Selchowstraße

Completed

Cable trench to remain open until August 2026

Thomas-Müntzer-Straße

Completed

Wassermannstraße

Road closed due to cable trench works until August 2026

Wünschelburger Gang

Pit closed, surface storage

Zinsgutstraße

Completed and opened to traffic

Temporary asphalt, concrete restoration to follow

Please note that cable laying is currently taking place in isolated streets.

Expected disruptions during construction work

  • During construction work, there will be temporary restrictions/partial closures on public roads.
  • Temporary noise is to be expected during construction work on weekdays from 7 am to 8 pm (depending on the season).

Note: Emergency routes and access to private properties will remain open.

Contact

Yvonne Post
Consultant Citizen Dialogue

T 030 49202 0294
(customer contact, Mo-Fr, 8 am - 6 pm)

[email protected]

Broschure Restructuring of grid in Treptow-Köpenick

in German language only