Restructuring of grid in Treptow-Köpenick
To increase capacity and improve security of supply, we are laying new high-voltage cables in the district.
The images are intended to illustrate underground cable construction work and do not depict any of the upcoming construction sites.
Berlin's increasing demand for electricity makes it necessary to expand the power grid. We will therefore more than double our capacity by 2033.
From the second quarter of 2025, new high-voltage cables will be laid in Treptow-Köpenick for this purpose. The construction work is expected to be completed by the third quarter of 2026.
Construction work schedule
The cable work will be carried out during ongoing operations. In order to ensure the power supply at all times, the planned work will be carried out sequentially in different construction phases.
The grid restructuring covers the districts of Adlershof Ost, Spindlersfeld and Altstadt-Kietz Köpenick. The following streets or sections of streets are affected by the measures:
| Streets respectively sections of streets | Activities |
|---|---|
| Alter Markt |
Completed |
| Flemmingstraße |
Underground cable works completed Flushing test at the junction with Gutenbergstraße completed Connection to the pipeline route expected from mid-May |
| Freiheit |
Flushing work completed Connection to the pipeline route and civil engineering works: from 9 April until mid-May 2026 (expected) |
| Freystadter Weg |
Completed - cable assemblies Closed until June |
| Gellertstraße |
Closed Road closed due to cable trench works until 1 June 2026 |
| Landjägerstraße |
Completed on 9 April 2026 |
| Lohnauer Steig | Completed – Cable installation: Trench to remain open until the end of June 2026 |
| Lüdersstraße | Roadworks until mid-May 2026 |
| Oberspreestraße | Civil engineering works are expected to continue until July 2026 |
| Radickestraße |
Completed except for the Nipkowstraße junction Cable trench until 1 June 2026 |
| Selchowstraße |
Completed |
| Thomas-Müntzer-Straße |
Closed Road closed due to cable trench works until 1 June 2026 |
| Wassermannstraße |
Road closed due to cable trench works until the end of June 2026 |
| Wünschelburger Gang |
Completed - cable assemblies |
| Zinsgutstraße |
Completed and opened to traffic Temporary asphalt, concrete restoration to follow |
Please note that cable laying is currently taking place in isolated streets.
Expected disruptions during construction work
- During construction work, there will be temporary restrictions/partial closures on public roads.
- Temporary noise is to be expected during construction work on weekdays from 7 am to 8 pm (depending on the season).
Note: Emergency routes and access to private properties will remain open.