Restructuring of grid in Treptow-Köpenick

To increase capacity and improve security of supply, we are laying new high-voltage cables in the district.

The images are intended to illustrate underground cable construction work and do not depict any of the upcoming construction sites.

Berlin's increasing demand for electricity makes it necessary to expand the power grid. We will therefore more than double our capacity by 2033.

From the second quarter of 2025, new high-voltage cables will be laid in Treptow-Köpenick for this purpose. The construction work is expected to be completed by the third quarter of 2026.

Construction work schedule

The cable work will be carried out during ongoing operations. In order to ensure the power supply at all times, the planned work will be carried out sequentially in different construction phases.

The grid restructuring covers the districts of Adlershof Ost, Spindlersfeld and Altstadt-Kietz Köpenick. The following streets or sections of streets are affected by the measures:

Streets respectively sections of streets Activities 
Alter Markt 

Completed

Flemmingstraße

Underground cable works completed

Flushing test at the junction with Gutenbergstraße completed

Connection to the pipeline route expected from mid-May

Freiheit

Flushing work completed

Connection to the pipeline route and civil engineering works: from 9 April until mid-May 2026 (expected)

Freystadter Weg

Completed - cable assemblies

Closed until June

Gellertstraße

Closed

Road closed due to cable trench works until 1 June 2026

Landjägerstraße

Completed on 9 April 2026

Lohnauer Steig Completed – Cable installation: Trench to remain open until the end of June 2026
Lüdersstraße Roadworks until mid-May 2026
Oberspreestraße Civil engineering works are expected to continue until July 2026
Radickestraße

Completed except for the Nipkowstraße junction

Cable trench until 1 June 2026

Selchowstraße

Completed

Thomas-Müntzer-Straße

Closed

Road closed due to cable trench works until 1 June 2026

Wassermannstraße

Road closed due to cable trench works until the end of June 2026

Wünschelburger Gang

Completed - cable assemblies

Zinsgutstraße

Completed and opened to traffic

Temporary asphalt, concrete restoration to follow

Please note that cable laying is currently taking place in isolated streets.

Expected disruptions during construction work

  • During construction work, there will be temporary restrictions/partial closures on public roads.
  • Temporary noise is to be expected during construction work on weekdays from 7 am to 8 pm (depending on the season).

Note: Emergency routes and access to private properties will remain open.

Contact

Yvonne Post
Consultant Citizen Dialogue

T 030 49202 0294
(customer contact, Mo-Fr, 8 am - 6 pm)

[email protected]

Broschure Restructuring of grid in Treptow-Köpenick

in German language only