Skip to main contentSkip to navigationSkip to search

Our service

Our online service

Customer requests
030 49202 0294
Monday - Friday, 8am - 6pm

Replacement construction of the Mitte grid node

We are investing in your neighbourhood’s future, and thus in maintaining and expanding a secure electricity grid.

More and more charging stations for electric vehicles and photovoltaic systems on roofs and balconies are shaping Berlin’s cityscape. And in future, Berlin’s electricity grid will also be used for part of the heat supply. To ensure that our electricity grid is reliably equipped for all these tasks, we are modernising and expanding our Mitte grid node.

A modern, cube-shaped brick building with vertical window slits stands on a grey pavement against a clear blue sky. Adjacent buildings are visible in the background.

3D-Visualisierung of the front view

Information on the planned construction work

The construction project is divided into the following construction phases:

  1. 4th quarter 2024 to 1st quarter 2025: preparations for the demolition of buildings on the Stromnetz Berlin site 
  2. 2nd quarter 2025 to 4th quarter 2025: above-ground demolition of an office and warehouse building
  3. 4th quarter 2025 to 2nd quarter 2026: demolishing foundations and creating an excavation pit
  4. 3rd quarter 2026 to 1st quarter 2028: constructing the shell
  5. 1st quarter 2028 to 3rd quarter 2029: producing the façade and carrying out interior work
  6. 3rd quarter 2029 to 1st quarter 2030: installing cable conduits
  7. 4th quarter 2029 to 1st quarter 2033: installing the system equipment in the building and commissioning it
  8. 2nd quarter 2033 to 4th quarter 2034: moving the cable to the new grid node (relocation and connection)
  9. 3rd quarter 2034 to 3rd quarter 2035: dismantling the technical equipment in the old network node
Three-story contemporary brick building with narrow vertical windows, flat roof, and minimalist design set against a clear blue sky.

3D-Visualisierung of the back view

Restrictions during construction work

Construction work is rarely silent, nor does it take place without restrictions. You should expect the following disruptions during the construction period:

  • Temporary restrictions or closures on public roads.
  • Work will take place on weekdays between 6 a.m. and 8 p.m. (depending on the season) and will lead to increased noise levels during certain phases.
  • Construction noise will not occur throughout the entire construction period, but only during individual phases that are necessary for the construction work.
  • Access to private properties will remain unaffected, but if access routes are affected, individual arrangements will be made on site with the responsible construction company.
  • No planned power cuts are expected.
  • Emergency routes and waste disposal will remain unaffected. Please note any notices posted by the BSR.

Contact

Yvonne Post
Consultant Citizen Dialogue

T 030 49202 0294
(Customer contact, Mo-Fr, 8am - 6pm)

[email protected]

Illustration showing construction equipment and an electrical box, with text indicating the renewal of the power grid and technical energy distribution systems in Neue Mitte by Stromnetz Berlin.

Flyer grid node Mitte

In German language only.

Our brochure