Replacement construction of the Mitte grid node
We are investing in your neighbourhood’s future, and thus in maintaining and expanding a secure electricity grid.
More and more charging stations for electric vehicles and photovoltaic systems on roofs and balconies are shaping Berlin’s cityscape. And in future, Berlin’s electricity grid will also be used for part of the heat supply. To ensure that our electricity grid is reliably equipped for all these tasks, we are modernising and expanding our Mitte grid node.
3D-Visualisierung of the front view
Information on the planned construction work
The construction project is divided into the following construction phases:
- 4th quarter 2024 to 1st quarter 2025: preparations for the demolition of buildings on the Stromnetz Berlin site
- 2nd quarter 2025 to 4th quarter 2025: above-ground demolition of an office and warehouse building
- 4th quarter 2025 to 2nd quarter 2026: demolishing foundations and creating an excavation pit
- 3rd quarter 2026 to 1st quarter 2028: constructing the shell
- 1st quarter 2028 to 3rd quarter 2029: producing the façade and carrying out interior work
- 3rd quarter 2029 to 1st quarter 2030: installing cable conduits
- 4th quarter 2029 to 1st quarter 2033: installing the system equipment in the building and commissioning it
- 2nd quarter 2033 to 4th quarter 2034: moving the 110 kV cable to the new grid node (relocation and connection)
- 3rd quarter 2034 to 3rd quarter 2035: dismantling the technical equipment in the old network node
3D-Visualisierung of the back view
Start of work and restrictions
- Work starts on the construction site at around 7.00 a.m. on working days.
- Working hours end at 8.00 pm at the latest.
- Access to the private properties will be maintained.
- There will be restrictions on public roads.
- Escape routes will remain open at all times.
- There will be no planned power interruptions.