Construction of the Marzahn substation

In a metropolis like Berlin, many components are needed to distribute energy: Electricity is transported via cables; transformed to another voltage level in substations and grid station.


In Märkische Allee there is a transformer station that has been in operation since the 1980s. The switchgear and transformers no longer meet the technical requirements and need to be replaced.

It is difficult to integrate new equipment into an existing building and to ensure the ongoing operation of the plant.

We are therefore building a new transformer station in the immediate vicinity.

Construction schedule

Q2 2022:  Start of civil enginieering work and construction of the excavation pit

10.11.2022: Laying of the foundation stone

Q1 2023:  Start of building construction

Q1 2024:  Toppin-out ceremony

Q2 2025:  Delivery of the transformers

Q1 2026: Installation of the switchgear

Q3 2027:  Commissioning of the new substation

Q3 2027:  Dismantling of old transformer station begins

Q4 2028:  Completion and closur of the project

 Work on the construction site starts at 07:00. Working hours end at 18:00 at the latest.

No construction work will take place at weekends.

Work will be carried out with particularly low-noise equipment and aggregates (Blue Angel for particularly environmentally friendly products).