Connection in medium or high voltage
We support you gladly in the set up, change or dismantling of a connection for your company or large-scale trade.
The right voltage level for your system depends on the power requirements.
Information on the fees for a medium- or high-voltage connection.
10 kV medium-voltage grid
Establish, change and dismantling - submit a request
An overview of the process and the requirements for establishing a new medium-voltage connection in an openly operated medium-voltage ring can be found in the information sheet on connecting customer systems to an openly operated medium-voltage ring.
We require for the establish or a change of a connection:
- the completed forms E.1, E.2 and possibly E.8 of the VDE AR N 4110
- expected power requirements (net output),
- a scaled site plan that includes the local position of the property to be connected. If you already have a suggested location for your transfer station, include this on the site plan along with the desired cable route through the property or building.
Please send us the completed form E.1 of the VDE AR N 4110 for decommission your transfer station and dismantle the connection.
Please send your request by email to
or by post to
Stromnetz Berlin GmbH
Netzvertrieb – Netzanschluss
10871 Berlin
Forms TAR medium voltage from appendix E of VDE AR N 4110
All documents in German language only.
Contract documents
Along with the quote for your connection to the medium-voltage grid, you will also receive one of the following versions of the grid connection contract:
1. If you use the connection yourself, you will receive a contract which regulates both the grid connection and connection usage
2. If your connection is used by a third-party, you, the power recipient,
- will receive a grid connection contract
sample copy of grid connection contract - and the connection user will receive a connection usage contract
sample copy of connection usage contract
The contract also contains the following attachments:
- General specifications and technical requirements for grid connections and connection usage in the medium-voltage and high-voltage grids
- Property boundary (only applies to the grid connection contract and the combined grid connection/connection usage contract):
Property boundary measuring field
Historically, in the case of existing connections, the following property boundaries are also conditionally available:
- Property boundary cable termination
- Property boundary bus bar branch
- Property boundary transfer control panel
Note: Further explanations regarding terms such as power recipient, connection user, grid connection contract and connection usage contract can be found in our glossary.
The set up or change of connections in the medium- and high-voltage grid takes place after 17 EnWG in connection with our „General and technical conditions for connection and connection use in the medium- and high-voltage grid“.
All documents in German language only.
Technical documents
The technical requirements are to be taken into account when planning, constructing, connecting and operating customer systems connected to the medium-voltage grid.
Technical requirements for medium voltage grid, version 2024, valid from 01.04.2024
Appendices
Appendix 1 - Rated value
Appendix 2 - Connection principles
Appendix 4 - Measuring transformer
Appendix 5 - TAR 4110 Forms
Appendix 6 - Checklists
TB3304 - Cable conduit ditches customer property
TB3312 - Medium-voltage switchgear in customer and grid stations
TB3340 - Remote control of network and customer stations in the medium voltage grid
TB3350 - Compact grid stations
TB3351 - Assembly compact grid stations
TB3354 - Rooms for grid and customer grid stations
TB3371 - Electrical grounding
VN37 - Electrical grounding
Technical requirements measuring device
Technical requirements for grid security management
Explanations on the technical requirements for grid security management
Pictures
Picture 1.1
Picture 1.3
Picture 1.5
Picture 1.6
Picture 1.7
Picture 1.8
Picture 1.9
Picture 1.10
Picture 1.11
Additional documentation
Technical guideline for electricity stations used on construction sites 2009
All documents in German language only.
Approved equipment
Manufacturers of medium-voltage switch gears that are permitted to be installed in the distribution grid receive a corresponding certificate of approval from us before they are installed. If equipment from other manufacturers is installed, it must be checked and approved by the Distribution System Operator before use.
Overview of approved equipment:
The following manufacturers currently have permission to install approved switchgears in Berlin's medium-voltage grid:
All documents in german language only.
Carrying out electrical installation work
As a Distribution System Operator, we keep a directory that contains a register of electricians who are permitted to construct, expand, alter or maintain the systems on our distribution grid. When choosing your electrician, please ensure that he or she is registered in our directory and has the necessary credentials.
Connection of a station for providing power to a construction site
The following guidelines apply to temporary connections and to the operation of a customer-owned station for providing power to a construction site with a transformer of up to 630 kVA:
Technical guidelines for stations for providing power to a construction site 2009
If you require a temporary connected capacity greater than 630 kVA, our technical requirements apply. You will find the documents at 'Technical documents'
The application, planning and commissioning procedures and practices for stations for providing power to a construction site are identical to those that apply to an application for a transfer station connection.
At the moment, the individual connection costs are the only charge that applies to the connection of a station for providing power to a construction site. The connection of a station for providing power to a construction site does not currently require the customer to make a contribution towards building costs.
All documents in German language only.
Connection of standby generators
VDE-AR-N 4110 applies to the connection and operation of standby generators.
110 kV high-voltage grid
Establish, change or dismantling - submit a request
To establish or change a connection, we need:
- the completed forms E.1, E.2 and, if applicable, E.6 of VDE AR N 4120,
- a true-to-scale site plan in accordance with form E.4 of VDE-AR-N 4120,
- an overview circuit diagram according to form E.4 of VDE-AR-N 4120,
- the expected power requirement (power balance).
For the decommissioning of your substation and dismantling of the connection, please send us the completed form E.1 of the VDE AR N 4120.
Please send your request via email to [email protected]
or by post
Stromnetz Berlin GmbH
Netzvertrieb – Netzanschluss
10871 Berlin
TAR Hochspannung – forms from appendix E of VDE AR N 4120
Further information
Since 1 January 2015, the VDE-AR-N 4120 has replaced the Transmission Code 2007 as well as the VDN guideline "Renewable Energy Power Plants on the High-voltage Network" (EEG-Anlagen am Hoch- und Höchstspannungsnetz) for 110 kV grid connections..
Information of the VDE on the topic of high-voltage connection
Note
Since May 2016, the "Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of Generators" has applied. At present, this is being transposed into national law by the relevant bodies, such as the VDE-FNN, and we expect an amendment to the technical connection regulations (TAR).*
* The VDE-AR-N 4120 forms part of the VDE regulations and can be purchased from VDE Verlag GmbH.
All documents in German language only.
Technical requirements for connection to the high-voltage grid
For planning, set-up, operation of and changes to customer installations (transformer stations and generation facilities) on the 110 kV high-voltage grid in Berlin, the technical requirements for the connection to the high-voltage grid (VDE-AR-N 4120*) as well as the supplementary Berlin-specific technical requirements for connection to the high-voltage grid in Berlin, apply.
Technical requirements for connection to the high-voltage grid in Berlin 2024 - valid from 01.11.2024
- Technical requirements for connection to the high-voltage grid in Berlin 2024 - valid from 01.11.2024
- Technical requirements high-voltage Berlin 2024 appendix 1 - rating
- Technical requirements high-voltage Berlin 2024 appendix 2 - technical data
- Technical requirements high-voltage Berlin 2024 appendix 3 - process data
- Technical requirements high-voltage Berlin 2024 appendix 4 - customer installation with regenerative generation
- Technical requirements high-voltage Berlin 2024 appendix 5 - forms VDE-AR-N 4120 appendix E
- Technical requirements high-voltage Berlin 2024 picture primary concept 6580.1
- Technical requirements high-voltage Berlin 2024 picture primary concept 6580.2
- Technical requirements high-voltage Berlin 2024 picture primary concept 6580.3
- Technical requirements high-voltage Berlin 2024 picture primary concept 6580.4
- Technical requirements high-voltage Berlin 2024 picture protection concept 6588.1
- Technical requirements high-voltage Berlin 2024 picture protection concept 6588.2
- Technical requirements high-voltage Berlin 2024 picture protection concept 6588.3
- Technical requirements high-voltage Berlin 2024 picture protection concept 6588.4
- Technical requirements high-voltage Berlin 2024 picture auxiliary power and control technology concept 6655.1
- Technical requirements high-voltage Berlin 2024 picture auxiliary power and control technology concept 6655.2
- Technical requirements high-voltage Berlin 2024 picture auxiliary power and control technology concept 6655.3
- Technical requirements high-voltage Berlin 2024 picture auxiliary power and control technology concept 6655.4
* The VDE-AR-N 4120 forms part of the VDE regulations and can be purchased from VDE Verlag GmbH.
All documents in German language only.
Connection according to KraftNAV
Applicants for a grid connection request in accordance with the Power Station Grid Connection Ordinance (Kraftwerksnetzanschlussverordnung - KraftNAV) also use the documents from our requirements for connection to the high-voltage grid in Berlin.
Fees
Connection fees
Once the boundary conditions (including power requirements, location of the planned customer-owned transfer station and the cable route through the customer property) have been clarified, we will provide you with an individual quote for establishing a connection between your transfer station and our medium-voltage grid.
The quote also sets out the connection costs for the connection to our medium-voltage grid and a contribution to building costs.
The contribution to building costs is in line with the recommendations made by the Federal Network Agency. To establish this fee, the published unit price of the access grid level in force when the contract was concluded or adapted is multiplied by the contractually agreed provision of power:
Contribution to building costs = Annual unit price (≥ 2,500 h/a) of the grid level x appointed power (kVA)
- General information from the Federal Network Agency on the construction cost subsidy
- Federal Network Agency position paper on charging contributions to building costs for grid connections in the area of grid levels above low-voltage (BK 6p-06-003 dated 05/01/2009) (PDF 44 kB)
- Price sheets of grid usage fees
Note: Some connection versions and additional actions may entail extra costs which you must bear in addition to the costs of a regular connection.
Price sheet reactive energy
When withdrawal electrical energy, a displacement factor (cos Phi) between 0.9 inductive and 1 must always be observed. If this is not the case, no reactive work is calculated according to the following price sheets.